The construction company staff increases to accelerate the works of Moll.
A dozen workers rush jobs with the aim of finalizing the nearest part to Ports before the arrival of Easter.
For several weeks, the contractor of the works of semipeatonalización running on the first line of Port de Pollença has increased the number of workers in order to accelerate the project and fulfill the stipulated time. It is recalled that the middle of last December, the opposition claimed that the works progressed at a very slow pace and pollencí government team had to intervene to require the builder to resume building after finding that only three workers working in pedestrianization project.
The Deputy Mayor of Urban Pollença, Tomeu Encrypt Bennàssar (Junts Avançam), confirmed yesterday that these days a dozen workers work in construction in the first line and expressed confidence that the work can meet the timing and completion of the first phase before the next start of the high tourist season. "It is true that so far has not been a very high rate, but so is that progress has been made," said the councilman.
Later in the industry
The most advanced part of the project coincides with the area that is the responsibility of Ports de les Illes Balears. In this sector "it is only the placement of the pavement and facilities that do not pass on sidewalks, and the installation of new lighting, usually the end." The company has also removed all the debris that was accumulated at the request of the City Council because, Encrypt, "offered a picture of neglect."
The Deputy Mayor added that the company knows that the works must be completed in the scheduled time and "If they see that they will meet deadlines incorporate more workers" because the construction "does not extend the work more than necessary."
The works were awarded in the last legislature the company INCOC by the Consortium plazas Tourist, dependent of the Ministry of Tourism. The agreement specifies that the Consistory pollencí is responsible for the technical direction of the works.
In this regard, the deadline set in the tender for the works was eight months, although the winning company offered as one of the best cut in two months the project. Work began last November, so that the city of Pollença expected to be completed next May, shortly before the start of the summer season.
The works will not be carried out in one fell swoop. It is scheduled to be paralyzed for about two weeks on the occasion of Easter, which this year coincides with the last week of March. The Consistory expected before the Easter break, the share Ports area is completely finished. After the festive period, the company will start to complete the first phase completely before June.
The second phase of the project has not yet been tendered. It is the central part correspondente to ride the first line of Moll and with the participation of the Consell de Mallorca, to be paved. The second phase will include the empowerment of bike lanes and other improvements on the project.